CDM Regulations 2015 for Groundworks: Principal Designer, Notifiable Projects and Construction Phase Plans
The Construction (Design and Management) Regulations 2015 (CDM 2015) apply to all construction work including groundworks. For notifiable projects (more than 30 working days with >20 simultaneous workers, or >500 person-days), the client must notify HSE, appoint a Principal Designer, and a Principal Contractor. Every project needs a Construction Phase Plan before groundwork commences. The most common groundworks CDM failures are inadequate pre-construction hazard identification (utilities, contamination, unstable ground).
Summary
CDM 2015 replaced the 2007 Regulations and significantly changed how health and safety is managed on construction projects. For groundworks specifically, CDM introduces requirements at three stages: pre-construction (identifying hazards and producing pre-construction information), during construction (Construction Phase Plan, site health and safety management), and post-construction (health and safety file).
Groundworks carry some of the highest CDM risk areas in construction: underground utilities, unstable excavations, buried contamination, proximity to existing structures, and heavy plant operations. A poorly prepared Construction Phase Plan that doesn't adequately address these risks is one of the most common compliance failures found by HSE when investigating groundworks accidents.
CDM 2015 applies to all construction work — not just large projects. A domestic extension (single client, domestic premises) has a simplified regime: some CDM client duties are transferred to the contractor. But the safety management duties — preparing a Construction Phase Plan, identifying hazards, providing a safe working environment — remain regardless.
Key Facts
- CDM 2015 — Construction (Design and Management) Regulations 2015 (SI 2015/51); replaced CDM 2007
- Applies to — all construction work, including groundworks, foundations, drainage, and demolition
- Client duty holders — Client, Principal Designer (PD), Principal Contractor (PC), Designers, Contractors, and Workers
- Notifiable project threshold — project lasting more than 30 working days with more than 20 workers simultaneously on site, OR over 500 person-days of construction work
- Notification — Client must notify HSE using F10 form (online) before construction phase begins
- Principal Designer — must be appointed by the Client on projects with more than one contractor; manages pre-construction H&S information
- Principal Contractor — must be appointed when more than one contractor; manages Construction Phase Plan
- Construction Phase Plan — must exist before groundworks commence; proportionate to project size and hazard
- Pre-construction information — hazard information gathered before design; includes utility surveys, site investigation, contamination assessments
- Health and Safety File — final project document; passed to building owner; must include as-built information on foundations, services, buried structures
- Domestic clients — on domestic projects with multiple contractors, principal contractor takes on client duties; single contractor projects — contractor takes on client duties
- HSE project notification — online at hse.gov.uk/f10/
Quick Reference Table: CDM 2015 Duty Holders and Groundworks Responsibilities
Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.
Try squote free →| Duty Holder | Key CDM Responsibility for Groundworks |
|---|---|
| Client | Commission ground investigation; gather pre-construction info; appoint PD and PC |
| Principal Designer | Identify and eliminate/reduce groundworks hazards at design stage; manage pre-construction info |
| Principal Contractor | Produce Construction Phase Plan; manage safety on site; coordinate sub-contractors |
| Groundworks Contractor | Follow CPP; competent workforce; trained for groundworks hazards; safe method statements |
| Designer (e.g. structural engineer) | Design foundations to avoid/reduce hazards; consider buildability and CDM |
Detailed Guidance
Pre-Construction Information for Groundworks
The Principal Designer is responsible for gathering pre-construction information. For groundworks this must include:
Utilities:
- Ground survey to identify buried services — gas, electricity, water, telecoms, drainage
- Use LSBUD (Lines and Cables Searches) and utility operator records; do not rely on drawings alone
- Mark up on site plan; confirm with CAT (Cable Avoidance Tool) and genny scan before excavating
- Minimum 500mm separation from any service line during excavation
Ground conditions:
- Ground investigation report (at minimum, trial pits with soil description and bearing capacity assessment)
- Historical maps to identify any made ground, previous buildings, wells, or contamination sources
- Groundwater level data — particularly relevant for deep excavations
Contamination:
- Environmental Desk Study and Phase 1 assessment for brownfield sites
- Phase 2 site investigation if any contamination indicators found
- Contamination affects: excavation disposal classification (waste classification), worker PPE requirements, concrete specification
Adjacent structures:
- Survey of all structures adjacent to excavations; note proximity, depth of foundations, condition
- For deep excavations within 6m of buildings, a pre-construction survey and monitoring of adjacent structures may be required
- Party wall agreements may be required (Party Wall etc. Act 1996)
Existing drainage and services in the ground:
- As-built drawings from utility operators (not always available)
- Drain CCTV survey if existing drainage routes may be affected
All pre-construction information must be provided to the Principal Contractor before the Construction Phase Plan is produced.
The Construction Phase Plan for Groundworks
The Construction Phase Plan (CPP) is not a generic document — it must address the specific hazards and methods for the project. For groundworks, a compliant CPP includes:
1. Project description and key parties
- Site address, client, PD, PC, key sub-contractors
- Programme overview; groundworks start and completion dates
2. Management arrangements
- Site rules (PPE, induction, permit systems)
- Communication arrangements; emergency contacts
- Welfare facilities
3. Groundworks-specific hazards and controls
| Hazard | Typical Control Measures |
|---|---|
| Underground utilities | CAT/genny survey; hand-dig zone (500mm around services); permit to dig |
| Unstable excavations | Risk assessment; trench support or battering; no entry without support ≥1.2m depth |
| Ground contamination | PPE; waste classification; site decontamination procedures |
| Groundwater | Dewatering plan; prevent groundwater from undermining foundations |
| Heavy plant interaction | Exclusion zones; trained operators; banks man for reversing plant |
| Concrete delivery | Vehicle management; PPE (alkali burns); COSHH assessment |
| Adjacent structures | Monitoring; settlement surveys; notification to neighbours |
4. Emergency procedures
- Collapse of excavation
- Utility strike (gas, electricity, water)
- Contamination exposure
5. Construction sequence
- Order of works; how each phase maintains safety
Proportionality: A domestic extension groundworks CPP can be a straightforward two to four page document addressing the specific hazards for that site. A city centre commercial development groundworks CPP for a basement excavation may run to 50+ pages. The content should be proportionate to the complexity and hazard level.
Notifiable Projects: When to Notify HSE
HSE must be notified on the F10 form when the construction phase is likely to exceed either threshold:
- More than 30 working days with more than 20 workers simultaneously on site at any point, OR
- More than 500 person-days of construction work
For groundworks: most domestic projects are not notifiable. A larger housing development, commercial project, or any project with significant programme duration is likely to be notifiable.
Online notification: Notify at hse.gov.uk/f10. The notification must be submitted by the Client before the construction phase begins. The F10 summary should be displayed on the site notice board.
Changes during construction: If the project scope changes and it becomes notifiable when it wasn't previously, the Client must notify HSE at that point.
Utility Strikes: The Most Common Groundworks CDM Failure
Utility strikes (hitting buried gas, electricity, water, or telecoms services) during groundworks are one of the most frequent serious incidents on construction sites. CDM 2015 requires the hazard to be identified and managed. The HSE's guidance "Avoiding danger from underground services" (HSG47) sets out the required approach:
- Plan — obtain all available utility records; interpret on a site plan
- Locate — use a CAT (cable avoidance tool) and signal generator (genny) to confirm routes on site; 'genny' injects a signal onto a pipe or cable which the CAT detects
- Avoid — design excavations to avoid utilities where possible; plan excavation routes
- Safe excavation — within 500mm of a utility service line, hand-dig only; no mechanical excavation
- Response — if a service is struck: gas leak → evacuate and call National Gas Emergency (0800 111 999); electricity strike → do not touch; move everyone clear; call 999 and the electricity network operator
A permit to dig (sometimes called a ground disturbance permit) is good practice and is required on many managed sites. It confirms that utility checks have been completed and that safe excavation procedures are in place.
Health and Safety File for Groundworks
At project completion, the Principal Designer prepares the Health and Safety File. For groundworks it must include:
- As-built foundation details (type, depth, dimensions, any variations from design)
- Survey records of buried services (as-laid positions)
- Ground investigation report and contamination assessment
- Any monitoring data (settlement, groundwater)
- Details of any unusual ground features encountered and how they were handled
- Drainage as-built drawings
The Health and Safety File is handed to the Client on project completion and must be retained for the life of the building. It provides essential information for any future works — renovation, extension, underpinning — that may affect the foundations or buried services.
Frequently Asked Questions
Does CDM apply to a self-build extension with one contractor?
Yes, CDM applies to all construction work. On a domestic project with a single contractor, the domestic client's duties are transferred to the contractor (Regulation 7). The contractor must prepare the Construction Phase Plan before starting and is responsible for managing H&S on site. The Project Designer duties also transfer in this scenario unless a separate designer is appointed.
Who appoints the Principal Designer on a groundworks project?
The Client appoints the Principal Designer. For most projects where an architect or structural engineer is designing the building, they will typically fulfil the Principal Designer role (with explicit appointment and acceptance of the duty). On groundworks-only contracts (e.g. a groundworks package on a larger development), the Principal Designer is typically appointed at the overall project level, not separately for the groundworks phase.
Is a method statement the same as a Construction Phase Plan?
No. A method statement describes how a specific operation will be carried out safely (e.g. how a trench will be excavated and supported). The Construction Phase Plan is the overarching health and safety management plan for the entire construction phase. Method statements are an important part of demonstrating how risks identified in the CPP will be controlled, but they are not the CPP itself.
What happens if groundworks start without a Construction Phase Plan?
Starting work without a CPP is a breach of CDM 2015 Regulation 12. HSE can issue a Prohibition Notice stopping work, or an Improvement Notice requiring a CPP to be produced. For notifiable projects where HSE has not been notified, the same enforcement applies. The Client, Principal Contractor, and individual contractors can all be prosecuted for CDM breaches.
Regulations & Standards
Construction (Design and Management) Regulations 2015 (SI 2015/51) — primary CDM legislation
HSE L153 — Managing health and safety in construction — CDM 2015 ACoP and guidance
HSE HSG47 — Avoiding danger from underground services; utility strike prevention
Work at Height Regulations 2005 (SI 2005/735) — overlaps with CDM for elevated work in groundworks
Control of Substances Hazardous to Health Regulations 2002 (COSHH) — contaminated ground handling
Waste regulations — contaminated spoil is controlled/hazardous waste requiring proper disposal
CDM 2015 Regulations — legislation.gov.uk — full text of Regulations
HSE CDM 2015 Guidance L153 — ACoP and supporting guidance
HSE HSG47 — Underground Services — utility strike avoidance
HSE F10 Notification — online project notification form
excavation safety trench support — trench safety and support requirements
strip foundation design — Building Regulations foundation compliance
raft foundation guide — alternative foundation type requiring engineer's design
building regs part h drainage — drainage design and groundworks coordination
Got a question this article doesn't answer? Squotey knows building regs, pricing and trade best practice.
Ask Squotey free →This article was generated and fact-checked using AI, with corrections from the community. If you spot anything wrong, please . See our Terms of Use.